East Alamosa Water & Sanitation District will be holding a Public Hearing on
September 29, 2020 at 6:00 pm for a proposed rate increase.  The purpose of the fee increase is to support a Waterline Improvement and Future Projects.  This hearing will be held via Zoom,
please use the information below to join the hearing:
https://us02web.zoom.us/j/81752904960
Or iPhone one-tap :  US: +12532158782,,81752904960# or +13462487799,,81752904960#
Or Telephone: Dial US: +1 253 215 8782 or +1 346 248 7799 or +1 669 900 6833 or +1 301 715 8592 or +1 312 626 6799 or +1 929 205 6099
Webinar ID: 817 5290 4960

Water Distribution

· Water lines in the Waterline Improvement & Replacement Project are approximately 44 years old

· Water lines degrade and become brittle over time, making point repairs and new line tie-ins difficult, more frequent, and more expensive

· Pipe size in some areas is too small to carry adequate fire fighting flow (typically 1,500 gpm)

· There are currently not enough fire hydrants in the Capital Improvement Area as dictated by the City of Alamosa Fire Chief.  There will be 18 new hydrants installed.

 

Financial Considerations

· East Alamosa Water District received a grant of $10,000 in December 2019 from Colorado Water Resources & Power Development Authority to complete the Pre-Loan Planning Grant and Project Needs Assessment. 

· East Alamosa Water District received a Principal Forgiveness Grant of $243,952 in May 2020 from Colorado Water Resources & Power Development Authority for the Design and Engineering.

· An application was submitted to the Department of Local Affairs for an Energy Impact Assistance Fund grant in the amount of $1,000,000 to be considered in October.

· East Alamosa Water District is committing $500,000 from financial reserves towards this project.